Re: Multi Level Finite Scheduling in PP/DS

$
0
0

Hi Frank,

 

I've used a copy of the SAP_BCTP on the Global parameters. Only difference, as I indicated on the previous post, was that I've used FIND SLOT as the Sched Mode on the "General Strgy Parameters" tab, while I used "SCHEDULE DEPENDENT OPERATIONS ACCORDING TO SCHED MODE" on the "Strategy Parameters for Dependent Objects" tab.

Finite Capacity is set to "AS SPECIFIED ON THE RESOURCE". To reiterate, with this setting, I'm trying to get the FG to shcedule Finitely, while the SFG should stay Block planned. Both resources must not get over-capacity situations (Utilization <= 100%).

 

Thanks